The Worcester Superior Court recently issued a potentially
landmark decision clarifying the risk that construction managers
assume when entering into CM-At Risk (CMR) contracts for public
building projects.
In Coghlin Electrical Contractors, Inc. v. Gilbane Building
Company, Gilbane and the Massachusetts Division of Capital
Asset Management (DCAM) entered into a CMR contract for the
construction of a state psychiatric facility with a guaranteed
maximum price (GMP) of $237 million. The electrical subcontractor,
Coghlin Electrical Contractors, Inc., requested a significant
increase in the cost of its subcontract due to alleged
mismanagement by construction manager Gilbane, including scheduling
issues, improper coordination with other subcontractors, and
failure to manage and complete wall and ceiling framing. Although
Gilbane issued a change order request to DCAM, the agency denied
the request because such an "inefficiency claim" was not allowed
under the CMR contract. Coghlin filed suit for cost recovery
against Gilbane, which in turn sued DCAM on the grounds that as the
contractual "owner" of the project, DCAM was legally responsible
for damages caused by design changes and design errors that caused
the additional subcontractor costs. The court dismissed Gilbane's
claim against the owner, holding that as construction manager, it
could not pass along the additional costs.
The court acknowledged that the suit presented a novel question:
whether a construction manager with planning and oversight
responsibilities as well as broad obligations under the CMR
contract to indemnify and hold harmless the owner would "trump the
long-standing Massachusetts common law principles to the effect
that 'where one party furnishes plans and specifications for a
contractor to follow in a construction job … the party furnishing
such plans impliedly warrants their sufficiency for the purpose
intended' [also known as the Spearin Doctrine]."
In answering this novel question, the court drew a clear
distinction between design-bid-build contracts and CMR contracts,
stating: "[I]n a traditional design-bidbuild project delivery
method, the owner is in the best position to ensure that the plans
and specifications prepared by its design professionals are
sufficient and adequate." While acknowledging that Massachusetts
common law traditionally has protected construction contractors
where an owner has supplied erroneous or ambiguous plans and
specifications, the court stated that because the particular
project had not followed a "traditional design-bid-build project
delivery method" and instead utilized an alternative delivery
method for public projects authorized pursuant to M.G.L c.149A, the
common law protections did not apply.
The court explained that unlike the traditional design-bid-build
methodology, the CMR process allows public entities to enter into a
contract with a construction manager before the design is finished.
Pursuant to M.G.L c.149A, "The purpose of entering into a contract
with the CMR contractor during the design phase of the project is
to involve the CMR contractor in project planning and to benefit
from the CMR contractor's expertise during the design phase or the
project." The court further differentiated the process of
allocating cost overruns in a CMR project from the design-bid-build
process. A CMR typically includes a guaranteed maximum price (GMP)
that includes the cost of the work, general conditions costs, and
the construction manager's fee. Absent change orders, the
construction manager assumes the risk for cost overruns that exceed
the GMP.
Given that a construction manager under a CMR contract assumes
additional duties and enhanced financial risk, the court determined
that the owner/construction manager relationship under a CMR
contract is not the same as the owner/general contractor
relationship found in a design-bid-build arrangement. The court
noted that the CMR contract at issue had imposed upon Gilbane
extensive "design review" responsibilities including the continuous
review of "drawings, specifications and other design documents …
for clarity, consistency, constructability,
maintainability/operability…" These design responsibilities also
came with "additional financial exposure" should something go
wrong, since CMR contracts also allocate project cost overruns
differently than traditional design-bid-build projects (e.g., a CMR
contractor is bound by a guaranteed maximum price, absent approved
change orders). Hence, as a result of the "material changes in the
roles and responsibilities voluntarily undertaken" by construction
managers in modern CMR contracts, "the protections that
Massachusetts courts historically extended to construction
contractors in the traditional design-bid-build contact … simply
are inapplicable to [CMR] contracts."
Gilbane's argument that DCAM was contractually required to issue
a change order because the changes affecting the walls and ceilings
were "changes in scope" proved unavailing to the court. So was its
argument that an exception to the underlying contract's broad
defense and indemnity obligations applied relating to claims for
design changes, errors or omissions. The court interpreted that
exception as strictly applying to the designer (an agent of DCAM)
and noted that because no claims had been brought against the
designer, the exception claimed by Gilbane was not relevant.
The Coghlin decision presents real concerns to those
engaged in CMR projects. Construction managers typically conduct
constructability reviews, but do not generally check all of the
architect's or engineer's designs and calculations in performing
their review. Nonetheless, this decision portends that the
construction manager essentially becomes the guarantor of design
specifications and that change orders are no longer a legitimate
means of seeking recourse for design-related problems that may be
encountered on a project. Unless overturned on a likely appeal,
there is a serious risk that the Coghlin decision will
disincentivize contractors from agreeing to CMR projects. Further,
CMR contract terms and conditions will have to be carefully
scrutinized and negotiated in order to avoid similar outcomes. In
addition, contract price proposals will have to be adjusted to
accommodate the enhanced risk associated with CMR contracts
pursuant to this decision.